I know meters are required to go outside. I was not going to replace the meter since they don't want to pull a permit and get it inspected. Just put new 4AWG CU in the existing conduit for 100A service.
1" conduit sounds about right and yes, it is all in conduit like the other job only the lines enter under the soffit and meter is in the basement.
The power company from my last job re-applied power before an inspection and the city denied us a pre-inspection and said they will just do 1 final one. Their house currently has power and no inspection has been done yet.
|